GE Frame 9FA+e, 230MW

Case study
GE Frame 9FA+e, 230MW

Original setup
OEM recommended

Environment
Desert/Coastal/Industrial

Challenge

Severe compressor damage due to corrosive deposits (sea salt).
Severe fouling and availability issues

Upgrade:

PanelS G4 + TurboMaster F8/E11

Result:

  • Zero need for off-line washing
  • Reduced wear and corrosion of compressor and hot path
  • Efficiency improvement >1.5%
  • ​5 MW increased average output

Pajatie 69 / 48600 Kotka / Finland / .(JavaScript must be enabled to view this email address)